Difference between revisions of "IBHLink S7++:Time Synchronisation with NetPro"
From IBHsoftec Wiki English
(→Projected Time Synchronisation with NetPro) |
|||
Line 10: | Line 10: | ||
− | The IBHLink S7++ / IBH Link S7++HS is engineered as PLC station in NetPro and networked via | + | The IBHLink S7++ / IBH Link S7++HS is engineered as PLC station in NetPro and networked via MPI |
or Profibus with the PLC. | or Profibus with the PLC. | ||
Latest revision as of 12:51, 19 September 2013
Projected Time Synchronisation with IBHLink S7++ or IBHLink S7++ HS.
Projected Time Synchronisation with NetPro
Within IBH Link setting Routing has to be activated :
The IBHLink S7++ / IBH Link S7++HS is engineered as PLC station in NetPro and networked via MPI
or Profibus with the PLC.
MLFB: 6ES7 412-2EK06-0AB0 V6.0 Rack 0, Slot 2
The IP and MPI/Profibus addresses need to be set equal to the addresses within the IBH Link S7++ / S7++ HS.
The selected NTP(Network Time Protocol) Server must be reachable.
Set the Synchronisation <On the MPI> to Master:
Within the properties of the networked PLC you have to set up the synchronisation as follows:
The Network project needs to be loaded in the IBH Link S7++/ IBH Link S7++HS and the networked PLC: